Data Centre Covenant: Power, planning, and the pace of AI

The Government wants considerably more data centre capacity in the UK. The challenge is that data centres need significant amounts of electricity, at a time when grid capacity is already constrained and the Government is trying to keep energy costs down.

The Data Centre Covenant (the Covenant), announced alongside the Autumn Budget, attempts to bring those competing issues together. As we have previously covered, the Covenant essentially offers strategic data centres greater Government support with power connections and planning in return for meeting enhanced expectations around energy, communities, the environment, jobs, and national security.

Our earlier article on the Budget considered the wider measures on grid connections and data centre planning, while Howard Felstead in our Planning team has looked at the potential planning implications of the Covenant itself.

In this article, we consider what happens when the Government's ambitions for AI meet the practical constraints of the energy and planning systems?

Can the energy system keep pace?

The scale of the demand is striking. The Government estimates that the UK will need 6 GW of AI data centre capacity by 2030 but data centres are already competing for capacity on a constrained electricity network.

That creates a tension at the heart of the Covenant. Data centres are expected to cover their “fair share” of the energy costs they create so that households and other businesses do not pick up the bill. The Government's view is that additional demand could, in time, help spread fixed system costs across more users but developers will also be expected to make credible commitments for the capacity they request and support a flexible and resilient energy system.

There is also the practical question of whether sufficient power can be delivered quickly enough. Some data centre developers are facing significant waits for grid connections. To address this, the Government intends to use powers under the Planning and Infrastructure Act 2025 to prioritise strategically important demand projects, including by reserving future grid capacity and reallocating capacity released when other projects leave the connections queue. Temporary on-site generation is also proposed as one possible bridge for “exceptionally strategic projects” but that raises its own questions around emissions and the compatibility of new gas-fired generation with wider clean power and net zero objectives.

Where the power comes from, what it costs, and how that additional demand affects the wider system will increasingly form part of development consenting.

Planning and power are increasingly difficult to separate

As we have previously considered, strategic data centres will be expected to provide additional community benefits, including through Local Benefit Plans, going beyond existing Section 106 and Community Infrastructure Levy requirements. The precise relationship between these different mechanisms is not yet clear.

There are environmental requirements too. New facilities are expected to be designed to achieve a Power Usage Effectiveness of 1.3 or better, minimise pressure on public water supplies and capture and reuse waste heat where there is a viable local user.

For developers, this arguably makes site selection an energy and planning exercise from the outset. Grid capacity, water constraints, potential heat users, and the ability to deliver meaningful community benefits may all need to be considered alongside the more conventional planning and land considerations.

What happens next?

There is still quite a bit of detail to come. Most importantly, the Government has not yet defined what constitutes a “strategic” data centre or the additional criteria projects will need to satisfy to access enhanced support.

The draft Data Centre National Policy Statement will also be important in determining how the Covenant translates into the consenting process for nationally significant infrastructure projects. Perhaps most fundamentally, developers will want to see whether the measures announced actually translate into shorter connection times in practice.

The Covenant is therefore an ambitious offer but not yet a complete solution. Faster planning will only take projects so far if the energy infrastructure needed to power them cannot keep pace.

How can we help?

Data centre projects increasingly sit at the intersection of planning, energy and infrastructure, and real estate.

Our planning and energy teams can help developers, investors, landowners, and major energy users:

  • Navigate the emerging Data Centre National Policy Statement and NSIP consenting regime

  • Consider how the Covenant tests and strategic designation may affect project development

  • Advise on Section 106 obligations, Local Benefit Plans, and community benefit arrangements

  • Consider grid connection strategy and the implications of power availability for project delivery

  • Address planning and consenting issues associated with on-site generation, heat reuse, and related energy infrastructure

The Covenant is still developing and so, early consideration of these issues may be particularly valuable for projects already in the pipeline.